Date:2019/08/12
On August 12, 2019, the new 10KV and 8000KVA transformer substation was tested for power transmission, which marked that Derui Chem had said goodbye to the history of power transmission by Yingchuang SanZheng cracking transformer. The original power transmission mode had great potential harm to the stable operation of the system, and the improved system provided more guarantee for the stable operation of the production system.
In sending trial production stage, because of load capacity and properties of several protection tripping event happened, through the joint efforts of all technical personnel, all seriously and repeated calculation, the end of the fixed value of the higher authority department gives the changes, finally obtained the satisfactory solution to the problem, now the power supply to run smoothly and orderly.
Jia Bing, Derui Chemical Assistant Workshop